Builders' Liens Update 2023


Course Date: March 7, 2023

Full Course Materials
Total: 5h 22min
Total Ethics: 28min

Welcome and Land Acknowledgement (9:00 – 9:10)

Teresa Sheward Program Lawyer, CLEBC, Vancouver
John S. Logan, KC Jenkins Marzban Logan LLP, Vancouver
David McKenzie Jenkins Marzban Logan LLP, Vancouver

What Land Can You Lien? (9:10 – 10:00)

  • new clarity on determining the improvement: JVD v. Skookum
    • a "single integrated improvement"
  • potential substantive defences to a lien
    • value of the land 
    • subcontracting the work
  • is benefit to the land required to lien?
  • if lien is invalid, recourse of owner?
  • need for statutory reform of the Builders Lien Act

Christopher J. Moore McLean & Armstrong LLP, West Vancouver
Michael B. Morgan Lawson Lundell LLP, Vancouver

First Nations Lands and Liens (10:00 – 10:40)

  • what can be liened on self-governed First Nations lands

David McKenzie Jenkins Marzban Logan LLP, Vancouver
Sasha Platz
Miller Titerle Law Corporation, Vancouver

BREAK (10:40 – 10:55)

The Claim of Lien: Both Form and Substance (10:55 – 11:25)

  • common mistakes that may invalidate a form of lien: A.W. Kennedy Construction Inc. v. Wan, 2021 BCCA 175
  • common mistakes in completing a claim of lien:
    • claimant
    • property
    • work description
    • debtor
    • amount owed
    • payment due date
    • address for service
  • consequences of mistakes in claims of lien

David Curtis Fasken Martineau DuMoulin LLP, Vancouver

When Does Time Start Running? (11:25 – 11:55)

  • triggers for running of time
  • substantial completion and certification of contracts
  • problems of certification
  • release of holdback
  • brief overview of Alberta builders' lien time regime

Dirk H. Laudan Borden Ladner Gervais LLP, Vancouver

LUNCH BREAK (11:55 – 12:40)

Mechanics of Getting Your Lien on Title (12:40 – 1:10)

  • latest cases
  • steps to not screw up your lien
  • best online tools for finding land to lien

David McKenzie Jenkins Marzban Logan LLP, Vancouver

Getting Liens Off Title (1:10 – 1:50)

  • removing defective liens
  • securing liens pending resolution
  • summary determination of holdback liability
  • removing liens from strata property

J. Marc MacEwing Clyde & Co Canada LLP, Vancouver

BREAK (1:50 – 2:00)

Closing Out a Project (2:00 – 2:50)

  • when can the lien holdback be released?
  • dealing with multiple lien claims
    • owner's perspective
  • priority issues with other claimants: CRA, garnishment, etc.
  • settlement issues
    • what to do if you have a holdout
    • specific distribution

Seema Lal Singleton Urquhart Reynolds Vogel LLP, Vancouver
David McKenzie
Jenkins Marzban Logan LLP, Vancouver

BREAK (2:50 – 3:00)

Ready for Use v. Substantial Completion (3:00 – 3:30)

Dirk H. Laudan Borden Ladner Gervais LLP, Vancouver
David McKenzie Jenkins Marzban Logan LLP, Vancouver
Marcus Turner Dentons Canada LLP, Vancouver

Builder's Lien Practitioner Pitfalls (3:30 – 4:00)

  • LIF current issues
  • ethics and law practice management issues
  • CPL's

Dirk H. Laudan Borden Ladner Gervais LLP, Vancouver
John S. Logan, KC
Jenkins Marzban Logan LLP, Vancouver
David McKenzie Jenkins Marzban Logan LLP, Vancouver